Quarterly Report 31 March 2010
LSE: RRS NASDAQ: GOLD

Quarterly Report 31 March 2010

Operations

LOULO

During the quarter Loulo produced 87 625 ounces, at a total cash cost of US$631/oz compared to 106 564 ounces in the previous quarter at US$512/oz. Total cash costs per ounce increased by 23% quarter on quarter following a decrease in the ounces produced and an increase in the unit costs of mining. The decrease in production resulted from a reduction in the average ore grade processed, as planned, coupled with lower throughput, partially offset by higher recoveries. The increase in unit mining costs results from an increase in total tonnes mined and adjustments to the rise and fall provisions,  additional mobilisation costs for opencast equipment and increased underground operating costs attributable to significant expenditure on equipment maintenance

The average gold price received during the quarter was US$1 110/oz, a 13% increase on the previous quarter (Q4 2009: US$984/oz) resulting primarily from no hedge positions being scheduled for the current quarter. 

This increase in the gold price received was offset by the reduced production and a higher cost base which resulted in a decrease in profits from mining activity of 19% to US$40.7 million (Q4 2009: US$50.4 million).

While the Loulo plant expansion project was successfully commissioned in the previous quarter, the increased throughput rates put pressure on some of the plant sections (notably the mill pumps and the crushers which were not working at higher performance levels) resulting in a requirement for the mine to raise preventive maintenance performance as well as highlighting some bottleneck areas in the circuit. The delay in getting the maintenance activities on track along with removing the bottlenecks of feeding the secondary crusher and the screening plant resulted in the decrease in tonnes processed. Both of these issues are being addressed by mine management.

The development at the Yalea underground showed some improvement as the new mining team settled in and started implementing the revised production plan which was formulated after the exit of the previous contractor. At the Gara underground mine blasting on the decline commenced at the end of the quarter and the first development ore from this mine is expected on schedule by the end of the current year.

 

LOULO RESULTS

Quarter

Quarter

Quarter

12 months

 

ended

ended

ended

ended

 

31 Mar

31 Dec

31 Mar

31 Dec

 

2010

2009

2009

2009

Mining

 

 

 

 

Tonnes mined (000)

10 380

9 451

5 728

27 977

Ore tones mined (000)

1 193

1 270

633

3 353

Milling

 

 

 

 

Tonnes processed (000)

794

862

685

2 947

Head grade milled (g/t)

3.7

4.1

3.7

4.2

Recovery (%)

93.1

92.8

87.1

87.7

Ounces produced

87 625

106 564

70 826

351 591

Average price received+ (US$/oz)

1 110

984

765

864

Cash operating costs* (US$000)

567

455

459

473

Total cash costs* (US$/oz)

631

512

501

522

Profit from mining activity* (US$000)

40 660

50 428

16 137

118 326

Gold sales*+ (US$000)

95 937

105 016

51 648

301 963



Randgold owns 80% of Loulo with the Government of Mali owning 20%.  The Government’s share is not a free carried interest.  Randgold has funded the Government portion of the investment in Loulo by way of shareholder loans and therefore controls 100% of the cash flows from Loulo until the shareholder loans are repaid.

Randgold consolidates 100% of Loulo and shows the non-controlling interest separately.

*    Refer to explanation of non-GAAP measures provided.

+   Includes the impact of 18 750 ounces delivered at US$428/oz in the quarter ended 31 December 2009 and 23 748 ounces delivered at US$441/oz in the quarter ended 31 March 2009. Also includes the impact of 84 996 ounces for the year ended 31 December 2009 delivered into the hedge at US$435/oz.

There were no hedge positions scheduled for the current quarter.


Mineral reserve update

During the quarter, the group released its annual mineral resource and mineral reserve declaration and the relevant extract relating to the Loulo mineral reserves is shown in the table below, including a comparison with 2008 figures: 

LOULO: MINERAL RESERVES* as at 31 December 

 

Attributable

 

 

 

 

 

 

 

Gold

 

Tonnes

Tonnes

Grade

Grade

Gold

Gold

(80%)

 

(Mt)

(Mt)

(g/t)

(g/t)

(Moz)

(Moz)

(Moz)

Category

2009

2008

2009

2008

2009

2008

2009

Proved

5.55

7.08

3.48

3.38

0.62

0.77

0.50

Probable

43.91

43.51

4.54

4.60

6.41

6.43

5.13

Total

49.45

50.59

4.42

4.42

7.03

7.20

5.63

 
*  Excludes Gounkoto which is reported separately.



MORILA

Morila produced 62 594 ounces during the quarter, 19% below that of the previous quarter of 76 920 ounces, slightly below the Life of Mine plan, primarily due to the drop in throughput. 

The average received gold price of US$1 113 was slightly higher than the previous quarter of US$1 110.

Total cash costs for the quarter of US$569/oz were in line with that of the previous quarter, a good achievement given the drop in the grade of ore processed and the drop in throughput during the current quarter.

Tonnes processed for the quarter of 980 000 tonnes was 8% below the previous quarter (Q4 2009: 1 062 000 tonnes) due to problems experienced with the primary crusher shaft which had to be replaced during the quarter. Subsequently the crusher availability has been increased from 45% to 92% following the implementation of an aggressive action plan strategised by the Morila team to overcome the situation. The process plant recovery for the quarter at 91.0% was in line with the previous quarter. 

Activity on the agri-business plans, which is part of the Morila closure strategy, continued with the completion of a draft feasibility study conducted by the Ingenieurs-Conseils en Technique de Development (ICOTED) and a local Malian company Enterprice Malienne Sabunnyuman (EMAS) selected to develop a 50 hectare irrigation project. This is part of the agri-business action plan implementation to ensure sustainable development after the cessation of Morila operations currently scheduled for 2013. 

 

MORILA RESULTS

Quarter

Quarter

Quarter

12 months

 

ended

ended

ended

ended

 

31 Mar

31 Dec

31 Mar

31 Dec

 

2010

2009

2009

2009

Mining

 

 

 

 

Tonnes mined (000)

-

-

3 377

3 657

Ore tones mined (000)

-

-

1 425

1 620

Milling

 

 

 

 

Tonnes processed (000)

980

1 062

1 053

4 303

Head grade milled (g/t)

2.2

2.5

3.2

2.7

Recovery (%)

91.0

91.1

92.3

91.4

Ounces produced

62 594

76 920

98 718

341 661

Average price received (US$/oz)

1 113

1 110

903

968

Cash operating costs* (US$000)

504

502

334

422

Total cash costs* (US$/oz)

569

569

388

480

Profit from mining activity* (US$000)

32 288

41 565

50 828

166 713

Stockpile adjustment (US$/oz)#

185

187

(95)

98

Attributable (40% proportionately
consolidated)

 

 

 

 

Gold sales (US$000)

27 166

34 137

35 650

132 231

Ounces produced

25 038

30 768

39 487

136 664

Profit from mining activity* (US$000)

12 914

16 626

20 331

66 685



*   Refer to explanation of non-GAAP measures provided.

#  The stockpile adjustment per ounce reflects the charge expensed/(credit deferred) in respect of stockpile movements during the period divided by the number of ounces produced.  The total cash cost per ounce include non-cash stockpile adjustments.


Mineral reserve update

The mineral reserve base for Morila as at end of 2009 is tabulated below with a comparison to figures at the end of 2008: 

MORILA: MINERAL RESERVES as at 31 December

 

Attributable

 

 

 

 

 

 

 

Gold

 

Tonnes

Tonnes

Grade

Grade

Gold

Gold

(40%)

 

(Mt)

(Mt)

(g/t)

(g/t)

(Moz)

(Moz)

(Moz)

Category

2009

2008

2009

2008

2009

2008

2009

Proved

9.85

13.74

1.74

2.02

0.55

0.89

0.22

Probable

6.91

6.88

1.14

1.14

0.25

0.25

0.10

Total

16.76

20.62

1.49

1.72

0.80

1.14

0.32

 





Back