« previous page | next page »  

Operations and projects

Introduction picture

The Tongon project is located in northern Côte d'Ivoire, 628 kilometres north of Abidjan within the 671km2 Nielle permit. The total resource base exceeds 3 million ounces.

TONGON PROJECT

A prefeasibility Type 2 study was completed in June 2002 which demonstrated that the Tongon project could meet the company's criteria for investment and a Type 3 feasibility study was initiated. After an initial 16 drillhole programme, further drilling and on-site feasibility study work was put on hold due to the political conflict in the Côte d'Ivoire.

In 2005 all aspects of the Tongon project were reviewed, the financial parameters used in the June 2002 prefeasibility study were updated to reflect December 2005 market conditions. The total resource base was confirmed at more than 3 million ounces.

UPDATED PARAMETERS

On the basis of this updated economic assessment and even taking into account the recent inflation pressures in the industry, the project continues to meet the company's hurdle rates for further investment.

The project had been stalled at feasibility stage for the past couple of years while the country has been dealing with political instability and conflict, but with the relative calm that has returned, the team has recommenced its work programme.

Randgold Resources believes that the peace process in the country is now on track. Presidential elections scheduled for October 2006 have been postponed due to a delay in preparation until October 2007, after an agreement was reached among the rival parties. Officials of both the government ministries and the opposition have shown commitment to making the project work.

             
              Tonnes           Grade           Gold Attributable
  TONGON: (Mt) (Mt) (g/t) (g/t) (Moz) (Moz) (75%)
  MINERAL RESOURCES 2006 2005 2006 2005 2006 2005 (Moz)
         
 
 
 
 
img

Inferred

35.96 35.96 2.68 2.68 3.11 3.11 2.33
 
             
* See glossary of terms on website at www.randgoldresources.com.
 

During 2006, an eight hole 1 992 metre tactical diamond drilling programme was carried out and the results were used to plan a 30 000 metre feasibility drilling programme scheduled for the first half of 2007. The drilling programme was designed to allow the completion of a final feasibility study and for a production decision within two years of full recommencement of drilling activities.

The next phase of drilling will help the company understand the relatively complex geology of the southern zone, as well as add additional resources to the northern zone. The biggest risk seen by Randgold Resources in the project is timing - the company is confident the people and governing structures of Côte d'Ivoire are committed to peace. The completion of a successful final feasibility study would allow a production decision and financing arrangements to be made.

Subject to a positive outcome of the bankable feasibility and the current political process, the company believes development of the Tongon deposit is likely as the Côte d'Ivoire has favourable infrastructure to support a mining venture. Power, water and road access are available close to the site. The Tongon project will also allow Randgold Resources to maintain and expand its production profile, as the Loulo mine grows and production at its Morila mine tails off.

Tongon Project: Bankable Feasibility Kicks off with a 30 000 Metre Drilling Programme